Our house is getting more and more beautiful 
Current work processes in Galileo Batumi:
  In block A, the partitions separating the apartments are being completed;
   The agreement with the tenants on the terms of the white frame is completed;
   installation of the sewage system, Swiss brand Geberit;
   preparation of shafts for Kone elevators is completed;
   The facade door-window gluing works are in active mode;
  In block B, the slab of the 6th floor was poured;
   In block B, the agreement of the terms of the white frame with the owners begin.
 Our yard arrangement works are in progress;