Our house is getting more and more beautiful
Current work processes in Galileo Batumi:
In block A, the partitions separating the apartments are being completed;
The agreement with the tenants on the terms of the white frame is completed;
installation of the sewage system, Swiss brand Geberit;
preparation of shafts for Kone elevators is completed;
The facade door-window gluing works are in active mode;
In block B, the slab of the 6th floor was poured;
In block B, the agreement of the terms of the white frame with the owners begin.
Our yard arrangement works are in progress;
We will share news about other ongoing works with you step by step. Our team is ready 24/7 to answer all your questions and help you become part of our big family
Hurry, 75% of apartments are already sold!
Whatsapp/Viber/Telegram
593 18 72 72
Petre Bagrationi #169